VanBibber Lake Conservancy District Water System Improvements

VanBibber Lake Conservancy District Water System Improvements

Van Bibber Lake, IN

Conservancy District Water System Improvements

The Van Bibber Lake Conservancy District completed significant improvements to their water system in 2023. The $9.4 million project includes construction of a new water treatment facility and complete replacement of their distribution system. The new water treatment facility included an aerator with detention tank, new vertical pressure filters, and new building in order to reduce the very high levels of iron in the raw water. The new water distribution system included installation of 24,000’ of new 6” and 4” water main to replace the undersized and failing water mains under homes and structures. The project also included the installation of 430 new AMI water meters since the system was previously unmetered at each residence. This project will improve the water quality, pressure, and flow to all the residents of the Van Bibber Lake community. The project was funded with an Indiana Office of Community and Rural Affairs (IOCRA) grant, Indiana Finance Authority (IFA), State Revolving Fund (SRF) forgivable loan, and United States Department of Agriculture (USDA) Rural Development loan and grant.

Veedersburg Wastewater System Improvements 

Veedersburg Wastewater System Improvements 

Veedersburg, IN

Build-Operate-Transfer (BOT) Wastewater System Improvements

The Veedersburg Wastewater System Improvements project included improvements to the existing Wastewater Treatment Plant (WWTP) to improve overall efficiency of the treatment system and update critical pieces of equipment. The project included replacement of the antiquated aerated lagoon “biolac” treatment system with a new oxidation ditch and two secondary clarifiers, a new influent structure, replacement of the existing UV treatment system with a non-contact type UV system, post-aeration, conversion of the existing north clarifier to a digester, and various improvements to electrical and controls. In addition, the project included the replacement of five lift stations (Primary, Sherman Street, Main Street, College Street, and Viewer Hills) located throughout the Town of Veedersburg to replace deteriorated facilities and improve the operation and efficiency of the collection system.  The project utilized the Build-Operate-Transfer (BOT) delivery method and was funded in part by the State Revolving Fund (SRF) program.

The $9.5 million project was completed in the fall of 2023.

Attica CSO LTCP Phase 2/Wastewater Treatment Facility Renovation

Attica CSO LTCP Phase 2/Wastewater Treatment Facility Renovation

Attica, IN

CSO LTCP Phase 2/Wastewater Treatment Facility Renovation

HWC worked with Attica, Indiana to complete Phase 2 of the City’s mandated CSO LTCP project. 

The City’s CSO Long-Term Control Plan required a second and final phase, which included floatables screening of flows from the single remaining overflow outfall to remain operational and storage of approximately 750,000 gallons of combined sewer flows to meet IDEM’s design storm criteria. HWC was hired to develop a Preliminary Engineering Report for the CSO project and necessary improvements at the treatment facility to address depreciation and compliance needs. 

The plan developed included improvements at the treatment facility, including:

  • New influent/CSO screening structure, which complied with the floatables control requirement of the CSO LTCP and fine screening for all influent flows
  • New 750,000 gallon per day average flow/1.2 MGD peak flow oxidation ditch for biological treatment to replace the current trickling filter process
  • Conversion of existing primary clarifiers to secondary clarifiers
  • Conversion of the existing trickling filter tanks to CSO storage tanks, which will be filled by dedicated CSO pumps in the retrofitted influent wet well
  • Chemical feed systems and piping for nutrient (phosphorus) control
  • Implementation of a new plant-wide SCADA system for both biological and wet weather process control

Due to the re-utilization of existing structures and conversion to a new biological treatment process, significant construction sequencing considerations were required in the design of the project. HWC held working sessions with the plant staff during design and with both the contractor and staff during construction to ensure minimization of operational disruptions were realized through demolition and sequencing of construction activities.

The total project cost was approximately $5.5 million. HWC provided planning, design, construction engineering, and inspection services for the project.

Brown County SR 135 over Strahl Creek Bridge Rehabilitation Brown County

Brown County SR 135 over Strahl Creek Bridge Rehabilitation Brown County

Brown County, IN

SR 135 over Strahl Creek Bridge Rehabilitation

HWC is providing road and bridge design for this bridge rehabilitation project. The existing bridge is a three-span continuous concrete slab bridge that is in horizontal and vertical curves along SR 135 in Brown County. The structure is deteriorated, hydraulically deficient, and has scour problems. The main scope of work is a superstructure replacement with roadway improvements to tie back into the existing superelevated roadway and safety improvements to upgrade the existing guardrail. This project will also evaluate the potential of adding a fourth span to the bridge to provide the necessary hydraulic capacity. The maintenance of traffic will utilize temporary portable signals for phased construction. 

Martin County Bridge Inspection

Martin County Bridge Inspection

Martin County, IN

Bridge Inspection

HWC is currently under contract to provide complete inspection, documentation, load rating, scour assessments, asset management, and reporting of Martin County’s 44 bridges (2021-2024). Of the County’s 44 bridges, 12 bridges require fracture critical inspection, 10 require a 12 month inspection cycle, one requires an underwater inspection, and five require special inspections.