Porter County Meridian Road Structure Replacement

Porter County Meridian Road Structure Replacement

Porter County, IN

Meridian Road Structure Replacement

HWC designed a single-span reinforced concrete slab bridge to replace the existing structure. The new bridge will use 100% GFRP reinforcing, combined with specific concrete admixtures instead of typical steel rebar, to target a 100-year design life with little maintenance. The roadway design included a passing blister for a neighborhood entrance. HWC also completed right-of-way acquisition and utility coordination for a dozen utility relocations. The new bridge is scheduled for construction in 2026. Utility relocations are currently being completed.
 

Porter County Brummitt Road Small Structure Replacement

Porter County Brummitt Road Small Structure Replacement

Porter County, IN

Brummitt Road Small Structure Replacement

HWC was responsible for the design and replacement of Structure PI-001, Brummitt Road over Arm 19 of the Little Calumet River, in Porter County, Indiana.

The project included the removal and replacement of an existing 142” x 91” corrugated metal pipe arch structure. This project also included a new concrete headwall, wingwalls, removal of a secondary pipe culvert to create an open ditch, as well as reconstructing the asphalt roadway, guardrail removal and installation, and landscaping. Additional scour protection measures were taken by adding riprap at both the inlet and outlet of the new structure.

The project was completed in August 2025 with an approximate construction cost of $960,000.

 

Attica Water System Improvements

Attica Water System Improvements

Attica, IN

Water System Improvements

HWC completed a water utility planning study for the City of Attica. The recommendations included in the preliminary engineering report resulting from the study included improvements to the Town’s water supply, treatment, distribution, and storage system. The study was utilized to secure funding for the project from the Indiana Office of Community and Rural Affairs (IOCRA) and the Indiana Finance Authority’s (IFA) State Revolving Loan Fund (SRF). The project included new buildings and interior piping for the two water supply wells, electrical improvements for the wells including an emergency backup generator, new chemical disinfection equipment, replacement of undersized water mains along with valves and hydrants in the distribution system, and replacement of an existing 500,000-gallon water reservoir with a new 500,000-gallon bolted steel glass-lined ground storage tank. HWC provided all design and construction phase services for the $3 million project, which was completed in 2025.

Dana Utility Water System Improvements Phases 1 & 2

Dana Utility Water System Improvements Phases 1 & 2

Dana, IN

Utility Water System Improvements Phases 1 & 2

Phase 1: This $400,000 project was the first phase of a comprehensive system upgrade focused on the distribution system and reducing the amount of water lost in the system. The project was OCRA-funded and included improvements to the Town’s distribution system, including water main, valve, and hydrant replacements. HWC prepared the bidding documents and provided engineering services during construction.

Phase 2: HWC was retained by the Town of Dana to complete the planning, design, and construction phase management for Phase 2 of this project to improve the operation, reliability, and sustainability of Dana’s water system. This phase consisted of an overall improvements plan and included improvements to the water supply, treatment, and storage facilities in the system, along with the addition of new radio read meters in the distribution system.

Key highlights include:

  • Wellfield – New well pumps, new electrical service and control systems, and a new raw water transmission main
  • Water Treatment Facility – New aerator, backwash waste system improvements, new electrical and controls, and building improvements
  • Water Storage Tank – Demolition of the 100-year-old elevated tank and construction of a new 75,000-gallon elevated tank

The approximate $2 million project was bid in late 2021 with construction completed in early 2023. HWC managed all engineering and funding acquisition processes for the project.